Project Procurement And Pre Tender Method Statement Construction Essay

Contract procurement has an impact on project performance in terms of costs, time and quality. During one of the briefing meetings at the pre-tender stage of a construction project, your Director has interest in collaborative procurement method and need your advice. In addition, your Director has multiple sites going on at the same time and therefore many site offices. Critically explain why collaborative procurement would be beneficial between the site offices to your Director.

Masterman, (2002) defined a procurement system as, ‘the organizational structure adopted by the client for the implementation, and at times eventual operation, of a project.’

What Citation Formats Do You Support?

We hear “Can you write in APA or MLA?” all the time—and the answer’s a big yes, plus way more! Our writers are wizards with every style—APA, MLA, Harvard, Chicago, Turabian, you name it—delivering flawless formatting tailored to your assignment. Whether it’s a tricky in-text citation or a perfectly styled reference list, they’ve got the skills to make your paper academically spot-on.

While Love (1998) adopted the definition such that,

‘It is an organizational system that assigns specific responsibilities and authorities to people and organizations, and defines the relationships of the various elements in the construction of a project’.

There has been an increasing recognition that the conventional (traditional) approach to contract procurement is inadequate (Rowlinson, S. 1999). However, it has been noted that there are still relatively few procurement systems for clients to choose from. Each procurement system that is available delivers project success to a variable degree (Bowen, 1997).

In today’s context, it can be seen that client’s satisfaction is seen to be largely dependent on the selection of the most appropriate procurement methodology, and failure to select an appropriate procurement approach is recognized as a primary cause of a project failure (Masterman, 1996). However, which procurement route to undertake for a particular project be it building or infrastructure works depends on the objective and requirements in terms of its functionality, cost, time and quality set by the client. While the selection of an appropriate procurement system in an essential part of the building process, it is unlikely that an “ideal’ procurement system that satisfies is all criteria will be available to ensure success (Winter, 2005).

Are Paper Services Legal?

Yes, completely! They’re a valid tool for getting sample papers to boost your own writing skills, and there’s nothing shady about that. Use them right—like a study guide or a model to learn from—and they’re a smart, ethical way to level up your grades without breaking any rules.

There are many factors that influence the project performance and contract procurement certainly has an impact on costs, time and quality. However the procurement system will influence whether the project will be a separated procurement system (traditional), integrated procurement system (design & build and its variant), management oriented system (management contracting, construction management), or collaborative arrangement (partnering, Early contractor Involvement, ECI, e-tender). Figure 1 below shows the various forms of procurement systems.

CLIENT

Experience/inexperience

How Much for a Paper?

Prices start at $10 per page for undergrad work and go up to $21 for advanced levels, depending on urgency and any extras you toss in. Deadlines range from a lightning-fast 3 hours to a chill 14 days—plenty of wiggle room there! Plus, if you’re ordering big, you’ll snag 5-10% off, making it easier on your wallet while still getting top-notch quality.

PROJECT MANAGEMENT TEAM OPTIONS

In-house/external/in-house & external

PROCUREMENT TYPES

Separated/ (2) integrated/ (3) management oriented/ (4) collaborative

Will Anyone Find Out I Used You?

Nope—your secret’s locked down tight. We encrypt all your data with top-tier security, and every paper’s crafted fresh just for you, run through originality checks to prove it’s one-of-a-kind. No one—professors, classmates, or anyone—will ever know you teamed up with us, guaranteed.

Separated

Single-stage/sequential

Two-stage/accelerated

(2) Integrated

Do You Rely on AI?

Not even a little—our writers are real-deal experts with degrees, crafting every paper by hand with care and know-how. No AI shortcuts here; it’s all human skill, backed by thorough research and double-checked for uniqueness. You’re getting authentic work that stands out for all the right reasons.

Direct design & Build

Competitive design & build

Develop & construct

Turnkey

Why Are You Top for Research Papers?

Our writers are Ph.D.-level pros who live for nailing the details—think deep research and razor-sharp arguments. We pair that with top plagiarism tools, free revisions to tweak anything you need, and fast turnarounds that don’t skimp on quality. Your research paper won’t just shine—it’ll set the bar.

BOT

(3) Management Oreinted

Management contracting

Construction management

Who’s Behind My Essays?

You’re in good hands with degree-holding pros—many rocking Master’s or higher—who’ve crushed our tough vetting tests in writing and their fields. They’re your partners in this, hitting tight deadlines and academic standards with ease, all while tailoring every essay to your exact needs. No matter the topic, they’ve got the chops to make it stellar.

Deep & Marine

(4) Collaborative

E-procurement

Parterning

Is My Paper Original?

100%—we promise! Every paper’s written fresh from scratch—no AI, no copying—just solid research and proper citations from our expert writers. You can even request a plagiarism report to see it’s 95%+ unique, giving you total confidence it’s submission-ready and one-of-a-kind.

ECI

The various procurement options available reflect the fundamental differences in the allocation of risk and responsibility to match the characteristics of different projects and client needs (Winter, 2005). When client select the type of procurement system to be use, strategic consideration must be considered especially at the stage on deciding whether to appoint a designer (architect/engineer), integrator (contractor), manager (project manager) or a group of all 3 working collaboratively.

Under this approach the client can use any of the systems from any of the other categories either singly or in combination, or even a bespoke system of his/her own making but with the choosen systems(s) being implemented within a specific setting controlled by the client.

Collaborative arrangement (Partnering) as required by the director has some benefits especially for multiple sites and with many site offices running at the same time. The benefits of time, cost and quality is explained below.

Can You Do Any Citation Style?

Yep—APA, Turabian, IEEE, Chicago, MLA, whatever you throw at us! Our writers nail every detail of your chosen style, matching your guidelines down to the last comma and period. It’s all about making sure your paper fits academic expectations perfectly, no sweat.

Benefits of time: several studies have indicated that by using the partnering approach the largest benefit is from the design and management processes were the flow of information between all parties helps to reduce the design times as designers and contractor understand and are more efficient in working together. It allows for faster project times as the selection process is eliminated which can be costly and time consuming. The project can have an early start on site, shorter construction times and lower risk of time overruns. However, using strategic partnering is more beneficial as it can achieve a 50% time saving it firms use the correct management procedures.

Benefit to Costs. As partnering assures certainly in the projects in terms of design and construction results in fewer cost overruns, reduce claims and litigations and the project cost also reduced. This is one of the important part of the project where saving some of the cost can add value to other important works that may be required at the end of the project.

Benefits to quality: Partnering can certainly improve the quality standards in building and there are indications that as a result, there are reduced number of defects, hence less rework is required. This is again another important aspect of the project where quality standard not only maintain but improved. Effective partnering relationships will also benefits from the R&D and innovative thinking which assist to improve productivity and quality.

TASK 2:

Can I Adjust Instructions Later?

Absolutely—life happens, and we’re flexible! Chat with your writer anytime through our system to update details, tweak the focus, or add new requirements, and they’ll pivot fast to keep your paper on point. It’s all about making sure the final draft is exactly what you need, no stress involved.

As part of the pre-tender process for a contract bid document, for multi-storey building projects for various sites, you are required to write a pre-tender method statement. Prepare a pre-tender method statement that you will submit with your bid document.

Pre-tender method statement is one of the important parts in the pre-tender process. Method statement is a document detailing how a particular task or activity will be carried out. Its detail the particular risk or danger associated with the particular parts of the project. However an assessment of construction methods to be considered during the tendering is required. The objectives of preparing a method statement are as follows:

To enable managerial experience to be called upon during estimating, a demand is created for information relative to performance. Managers find it is necessary to record resources, quantities and time in order to contribute.

To enable data concerning new construction techniques and methods of handling materials to be included in an estimate. The method statement may be developed from work study data and planning cycles prepared for an alternative plant and labour situation.

How Do I Get Started?

It’s super easy—order online with a few clicks, then track progress with drafts as your writer works their magic. Once it’s done, download it from your account, give it a once-over, and release payment only when you’re thrilled with the result. It’s fast, affordable, and built with students like you in mind!

To permit the plant requirements for a project to be summarized for inclusion in the contract preliminaries or plant schedule.

To ensure the output and duration of different methods and machines is realistically matched.

To give guidance to the estimator on specific on specific bill of items relating to plant and labour requirement in order that realistic rates may be built up.

In this case study, a pre-tender method statement is to be prepared as part of the pre-tender process for a contract bid document for multi-storey building projects for various sites. Various formats for method statement can be used; like a pre-printed standard format that has been designed for repetitive works for familiar design such as in this case-study.

How Fast for Rush Jobs?

We can crank out a killer paper in 24 hours—quality locked in, no shortcuts. Just set your deadline when you order, and our pros will hustle to deliver, even if you’re racing the clock. Perfect for those last-minute crunches without compromising on the good stuff.

Information that is required on method statement includes the operation or work stage. Each operation requiring analysis of plant or method should be listed in the method statement, for example excavation work, formwork, concrete handling and placing, choice of plant for lifting precast floors or erecting steelwork.

Quality of work is also required where this is directly affect methods of construction, number of man-powers and machineries. Realistic methods of construction together with constructive alternative and sequencing of operations should be outlined clearly.

The summary of plant will assist in the preparation of the preliminaries plant element where an example is tabulated in the table below.

S/No

Operation

Can You Handle Complex Subjects?

For sure! Our writers with advanced degrees dive into any topic—think quantum physics or medieval lit—with deep research and clear, sharp writing. They’ll tailor it to your academic level, ensuring it’s thorough yet easy to follow, no matter how tricky the subject gets.

Quantity

method

Sequence of operations

Plant and labor

output

How Do You Meet Prof Standards?

We stick to your rubric like glue—nailing the structure, depth, and tone your professor wants—then polish it with edits for that extra shine. Our writers know what profs look for, and we double-check every detail to make sure it’s submission-ready and grade-worthy.

duration

1

Excavate over-site to reduce levels and remove to tip

70 x 100 x (ave.) 450mm = 3150 m2

What’s Your Editing Like?

Send us your draft and tell us your goals—we’ll refine it, tightening arguments and boosting clarity while keeping your unique voice intact. Our editors work fast, delivering pro-level results that make your paper pop, whether it’s a light touch-up or a deeper rework.

Excavate using hydraulic power shovels. Load excavated material direct into 8 cubic metre capacity lorries cart away to top

Alternative

Excavate using hydraulic backactor, track mounted 360 deg slewing machine laoading direct into lorries hymac 580 or similar

Site strip to commence after taking initial grid of levels

DITTO

Can You Pick My Topic?

Yes—we’ve got your back! We’ll brainstorm fresh, workable ideas tailored to your assignment, picking ones that spark interest and fit the scope. You choose the winner, and we’ll turn it into a standout paper that’s all yours.

1 banksman

Cat. 951 crawler tractor

4 lorries

1 banksman

40 m3/hr

35 m3/hr

3150/40 = 79 man-hr

Do You Do Quick Revisions?

Yep—need changes fast? We’ll jump on your paper and polish it up in hours, fixing whatever needs tweaking so it’s ready to submit with zero stress. Just let us know what’s off, and we’ll make it right, pronto.

90 man-hr

2

Excavate pad and strip foundations

300 mm of strip foundation bases say 200m3

Excavate shallow foundations using Rymac 580 as before and load direct into lorries

On stripping factory areas the excavation work to the factory area commence

Can You Outline First?

Sure thing! We’ll whip up a clear outline to map out your paper’s flow—key points, structure, all of it—so you can sign off before we dive in. It’s a handy way to keep everything aligned with your vision from the start.

1 banksman

1 Hymac

2 lorries

3

Concrete strip and pad foundations

100m3 ready mixed concrete

Ready mixed concrete to be discharged direct into foundations. Site access via hardcored formation

On fixing of bolt boxes to 6 pad foundations, concrete work may commence

Can You Add Data or Graphs?

Absolutely—we’ll weave in sharp analysis or eye-catching visuals like stats and charts to level up your paper. Whether it’s crunching numbers or designing a graph, our writers make it professional and impactful, tailored to your topic.

3 labourers

1 day/

4 to 6 bases

4

Erect steelwork and roof cladding

N/S/C

Contractor to prepare central area of floor slap with oversite hardcore for crane during erecation

Bases to be checked by steel-work contractor, prior to erection and leveling of bases to receive steelwork bases on one bay of portal to be complete prior to erection of steelwork.

N/S/C

10 days

How Do You Manage Big Projects?

We tackle each chunk with precision, keeping quality consistent and deadlines on track from start to finish. Whether it’s a dissertation or a multi-part essay, we stay in sync with you, delivering top-notch work every step of the way.

The content and description of the pre-tender method statement for the proposed construction of multi-storey building is outlined below.

Introduction

This method statement is prepared for the construction of propose multi-storey building project located at the site location indicated in site map. Before any work is commenced, the contractor shall confirm in writing to the engineers that the relevant site and survey works is true and accurate record of the condition of all properties, lands and crops inspected. The contractor shall clear the whole area with the boundary lines as shown in the drawing and shall exercise care and attention to ensure all the clearing activities and operation is confined with the boundaries and no damage is caused to any property or vegetation outside the boundary.

Site establishment

Where appropriate, the engineer shall arrange surveys to be carried out, in conjunction with the contractor and owner of the land, of all the condition of all properties, lands and crops which may be affected by the works. The sites includes the “work areas” and “borrows areas”, if any, indicated on the drawings and includes such other areas of roads, footpaths and lands which, in the opinion of the engineer, are necessary for the execution of the works. The contractors shall confine his constructional operations within the site, or such other areas of land as may be negotiated, and shall instruct his employees not to tre-pass.

Site accommodation

The contractor is to provide offices for the exclusive use of the Resident engineer. The location shall be determined by the contractor within the contract area and agreed by the supervising officer. Provide and maintain water, lighting and power supply and pay all the charges in connection therewith. The contractor also shall provide and maintain all necessary sheds and stores and remove the same from the site on completion of the works.

Site access

The contractor shall comply in all respects with all local road traffic regulations concerning the road site access, the warning light and guarding of the road works. The contractor shall construct and maintain diversion ways wherever the works will interfere with the existing roads, footways or other ways over which there is a public or private right of way. Before any work in or affecting the use of site access and main road is commenced, the contractor’s proposal method of working shall be agreed with, and confirmed in writing to, the engineer and the highway and police authorities.

Do You Follow Global Academic Rules?

Yes—we’ve got it down! Our writers switch seamlessly between UK, US, Australian, or any other standards, matching your school’s exact expectations. Your paper will feel native to your system, polished and ready for wherever you’re studying.

Materials and distribution

Unless specified to the contrary, all material shall be in accordance with the relevant British Standard (BS) and Code of Practices (CP). Should alternative requirement be provided by a BS and no one alternative be specified elsewhere in the contract, then before proceeding to execute the works or to order materials, the contractor shall give notice requesting further specification of such matter. The contractor shall submit list of suppliers from whom he propose to purchase the material for the execution of the work. If required by the engineer, the contractor shall submit to the engineer test certificates and samples furnished by the supplier or manufacturer of any material or article indicating compliance with the requirement of the contract. Materials shall store in the manner as to preserve their quality and condition to the standards required by the contract.

Sub-structure works

The contractor shall carried out all sub-structure works including earth work in such manner as to prevent erosion or slips, and limit working faces to safe slopes and height, and shall ensure that all surfaces have at all times sufficient gradient to enable them to shed water without causing erosion and to prevent ponding. The contractor shall provide and maintain all necessary temporary access roads and temporary drainage and shall divert and reinstate permanent drainage system. The purposed alignments and levels of temporary access roads shall be submitted to the engineer for approval prior to their construction.

Super structure

All super structure works such as ground beams, flooring and roof trusses shall be constructed in accordance to the design given by the engineer. The contractor shall supply and install all open mesh and steel plate flooring and structural members necessary for the support of flooring, walkways, staircases, hand railing, ladders etc. shown in the drawing unless otherwise stated.

External envelope

Before interfering with access to any property, the contractor shall provide satisfactory alternative arrangements. The contractor shall take necessary precautions to avoid causing any damage to roads, lands properties, trees and other features and during the currency of the contract, shall deal promptly with any complaints by owners or occupiers.

Mechanical and electrical services

The tenderer shall allow in his tender for providing a suitably qualified engineer with at least ten years working experience on similar installation to coordinate the civil, mechanical and electrical details and to advise the engineer of any changes. The specification covers, but is not necessary restricted to, the provision of an electrical supply, instrumentation, lighting and power for the complete works. This include construction, performances, installation and testing of electrical equipment such as electrical ducting, opening pockets, cable wiring, transformer cables, and termination etc. for both works on the site of the proposed new power supply to the building.

What is a progressive delivery and how does it work?

Progressive delivery is a cool option where we send your paper in chunks—perfect for big projects like theses or dissertations. You can even pay for it in installments. It’s just 10% extra on your order price, but the perks are worth it. You’ll stay in closer touch with your writer and can give feedback on each part before they move to the next. That way, you’re in the driver’s seat, making sure everything lines up with what you need. It saves time too—your writer can tweak things based on your notes without having to redo huge sections later.

Overall working program

The contractor shall provide the overall working program of the construction activities and to keep updating and reviewing for time to time the progress of the works, including the financial status, the material, manpower and other related works. Where required by the contract, the contractor shall provide record progress photographs taken as and what directed by the engineer.

Health, safety and welfare of work people

The contractor shall be responsible for the safety of all persons engaged in the execution of the work and shall take such safety precautions as are generally accepted as good civil engineering practice, including the provision of first aid equipment and personal trained in its use. The contractor shall appoint a “safety officer” who is responsible for safety inspection at the construction site.

Tags: Affordable UK Dissertation Services - Research Essay Assistance, Complete My Paper - Chicago/Turabian Citation Formatting, Dependable Online Homework Assistance with Annotated Bibliography, Excel in Homeworks with Case Study Support

Order|Paper Discounts

Why Choose Essay Bishops?

You Want The Best Grades and That’s What We Deliver

Top Essay Writers

Our top essay writers are handpicked for their degree qualification, talent and freelance know-how. Each one brings deep expertise in their chosen subjects and a solid track record in academic writing.

Affordable Prices

We offer the lowest possible pricing for each research paper while still providing the best writers;no compromise on quality. Our costs are fair and reasonable to college students compared to other custom writing services.

100% Plagiarism-Free

You’ll never get a paper from us with plagiarism or that robotic AI feel. We carefully research, write, cite and check every final draft before sending it your way.