In construction area, the accurate and complete of the cost estimation is the key to success profitability of the construction project. Cost estimation is utilized as one of the main implements of successful cost management for the project. A good estimator should understand in the construction materials, the method and system of the construction. This is very important for them to do the estimating as well as the labour and equipment required to complete the entire mission in their correct categorisation on time and on budget. In this task, we will try to discuss and estimated according to the task given which is excavation, formwork, reinforcement bar, BRC, concrete and brick wall. We should do the estimation for each task according to the calculation. But each task represented different calculation method. Therefore, we have to calculate according to the correct step to show the correct estimation for each task.
Find the rate per m3 for excavating a foundation trench starting at ground level in no exceeding depth 1.5, average 1.2m and for removing all surplus excavated materials from site using hand labour loading into 5m3 dumpers. Excavation is done 60% by hand and 40% by 1/4m3 excavator. Cost per hour is RM 85.00 including operator. A banksman is needed at RM40.00 per day. The spoil heap is deposited on ground before loading into lorry.
We hear “Can you write in APA or MLA?” all the time—and the answer’s a big yes, plus way more! Our writers are wizards with every style—APA, MLA, Harvard, Chicago, Turabian, you name it—delivering flawless formatting tailored to your assignment. Whether it’s a tricky in-text citation or a perfectly styled reference list, they’ve got the skills to make your paper academically spot-on.
A labourer will excavate 1m3 in 4 hours. This excludes throwing spoil into lorry for disposal. Loading of 5m3 of soul will take 6 men’s in 1.75 hours at RM4.00 per hour. For one trip including loading and uploading will take 2 hour. Cost of lorry including driver and fuel is RM 65.00 per hour. Bulking is 25%. Output of excavation for excavator and hand excavation are given for normal ground as 9m3/hour. Overhead and profit are charged on 15%. Cost for labour is RM 60/day
Approximate the rate (per m3) for specified works/activities
Topic
Calculation
Yes, completely! They’re a valid tool for getting sample papers to boost your own writing skills, and there’s nothing shady about that. Use them right—like a study guide or a model to learn from—and they’re a smart, ethical way to level up your grades without breaking any rules.
Cost (RM/1m3)
Excavation by hand (60%)
RM60/8hour x 4hour = RM30/m3
Prices start at $10 per page for undergrad work and go up to $21 for advanced levels, depending on urgency and any extras you toss in. Deadlines range from a lightning-fast 3 hours to a chill 14 days—plenty of wiggle room there! Plus, if you’re ordering big, you’ll snag 5-10% off, making it easier on your wallet while still getting top-notch quality.
RM30 x 0.6= RM18 /m3
18.00
Excavation by excavator (40%)
RM 40/8hour/9m3= RM 0.56 m3
Nope—your secret’s locked down tight. We encrypt all your data with top-tier security, and every paper’s crafted fresh just for you, run through originality checks to prove it’s one-of-a-kind. No one—professors, classmates, or anyone—will ever know you teamed up with us, guaranteed.
RM85/9m3= RM9.44/m3
RM 0.56 + RM9.44 = RM10/m3
RM10/m3 x 0.4= RM4/m3
4.00
Not even a little—our writers are real-deal experts with degrees, crafting every paper by hand with care and know-how. No AI shortcuts here; it’s all human skill, backed by thorough research and double-checked for uniqueness. You’re getting authentic work that stands out for all the right reasons.
Removing:
RM65 x 2 hour= RM130
6x 1.75hour x RM4=RM42
RM130+RM 42=5m +25%
Our writers are Ph.D.-level pros who live for nailing the details—think deep research and razor-sharp arguments. We pair that with top plagiarism tools, free revisions to tweak anything you need, and fast turnarounds that don’t skimp on quality. Your research paper won’t just shine—it’ll set the bar.
RM172=6.25 m3
1 m3=RM27.52
27.52
TOTAL:
You’re in good hands with degree-holding pros—many rocking Master’s or higher—who’ve crushed our tough vetting tests in writing and their fields. They’re your partners in this, hitting tight deadlines and academic standards with ease, all while tailoring every essay to your exact needs. No matter the topic, they’ve got the chops to make it stellar.
PROFIT (15%)
49.52 X 15%= 7.43
7.43
Cost of excavation work
100%—we promise! Every paper’s written fresh from scratch—no AI, no copying—just solid research and proper citations from our expert writers. You can even request a plagiarism report to see it’s 95%+ unique, giving you total confidence it’s submission-ready and one-of-a-kind.
45.52+6.83=52.35
Find unit rate per m3 for excavating a pit for pad, starting at ground level inclusive removing all surplus excavated materials from site using hand labour loading 6m3 into lorry. Excavation is done 2/5 by hand and 3/5 by excavator. The excavator cost is RM80.00 per hour including the operator. A banksman is needed at RM5.00 per hour.
a labourer will excavate 1m3 in 3.5 hour. This excludes throwing spoil into the lorry for disposal. Loading of 6m3 of soil will take 6 men’s in 1.75 hour at RM5.00 per hour. One trip including loading and unloading output of excavation for excavator and hand excavation is given for RM65/hour for normal soil . Assume output of excavator is 8.5m3/hour. Assume cost for labour is RM60/day. Overhead and profit are allowed at 10 %
Estimate the rate (per m3) for the specified work.
Yep—APA, Turabian, IEEE, Chicago, MLA, whatever you throw at us! Our writers nail every detail of your chosen style, matching your guidelines down to the last comma and period. It’s all about making sure your paper fits academic expectations perfectly, no sweat.
Topic
Calculation
Cost (RM/1m3)
Excavation by hand (2/5)
Absolutely—life happens, and we’re flexible! Chat with your writer anytime through our system to update details, tweak the focus, or add new requirements, and they’ll pivot fast to keep your paper on point. It’s all about making sure the final draft is exactly what you need, no stress involved.
RM60/8hour x 3.5hour = RM26.25/m3
RM26.25/m3 x 2/5= RM10.50 /m3
10.50
Excavation by excavator (3/5)
It’s super easy—order online with a few clicks, then track progress with drafts as your writer works their magic. Once it’s done, download it from your account, give it a once-over, and release payment only when you’re thrilled with the result. It’s fast, affordable, and built with students like you in mind!
RM 5/8.5m3= RM 0.59 m3
RM80/8.5m3= RM9.41/m3
RM 0.59 + RM9.41 = RM10/m3
RM10/m3 x 3/5= RM6/m3
We can crank out a killer paper in 24 hours—quality locked in, no shortcuts. Just set your deadline when you order, and our pros will hustle to deliver, even if you’re racing the clock. Perfect for those last-minute crunches without compromising on the good stuff.
6.00
Removing:
RM65 x 1 hour= RM65
6x 1.75hour x RM5=RM52.50
RM65+RM 52.50=6 m3
For sure! Our writers with advanced degrees dive into any topic—think quantum physics or medieval lit—with deep research and clear, sharp writing. They’ll tailor it to your academic level, ensuring it’s thorough yet easy to follow, no matter how tricky the subject gets.
6 m3= RM 117.50
1 m3=RM19.58
19.58
TOTAL:
PROFIT (10%)
We stick to your rubric like glue—nailing the structure, depth, and tone your professor wants—then polish it with edits for that extra shine. Our writers know what profs look for, and we double-check every detail to make sure it’s submission-ready and grade-worthy.
39.08 X 10%= 3.61
3.61
Cost of excavation work
39.08 + 3.61=52.35
Send us your draft and tell us your goals—we’ll refine it, tightening arguments and boosting clarity while keeping your unique voice intact. Our editors work fast, delivering pro-level results that make your paper pop, whether it’s a light touch-up or a deeper rework.
Calculate the cost per kilogram of 25mm diameter high yield steel reinforcement bars based on the following information. Given:
Material cost: 25mm diameter bars delivered to site = RM 1,250.00 per tonne
Using a labourer for Stacking and off-loading = RM5.00 per hour per 100kg
Tie wire is o.66kg/100kg of reinforcement bar at RM 3.20/kg
Allow spacers = RM4.00 per tonne of reinforcement bar
Yes—we’ve got your back! We’ll brainstorm fresh, workable ideas tailored to your assignment, picking ones that spark interest and fit the scope. You choose the winner, and we’ll turn it into a standout paper that’s all yours.
Allow for rolling margin RM 25.00 per tonne of reinforcement bar
Allow 5% wastage
Labour cost
One skilled labourer and one unskilled labourer at RM6.00 per hour and RM4.00 per hour respectively
Allow 10% idling time
Time analysis for 100kg of reinforcement bar:
.select = 20 minutes
Yep—need changes fast? We’ll jump on your paper and polish it up in hours, fixing whatever needs tweaking so it’s ready to submit with zero stress. Just let us know what’s off, and we’ll make it right, pronto.
Cut = 27minute
Bend = 35 minutes
Fix = 23 minutes
Hoist twice = 9 minutes
Overhead and profit = 15%
Topic
Sure thing! We’ll whip up a clear outline to map out your paper’s flow—key points, structure, all of it—so you can sign off before we dive in. It’s a handy way to keep everything aligned with your vision from the start.
Calculation
Cost (RM/kg)
Cost of Materials
RM1250/1000kg=RM1.25/kg
RM3.20 x 0.66 kg=RM1.25/kg
RM4/1000kg=RM0.003/kg
RM25/1000kg=RM0.03/kg
RM1.25/kg+ RM1.25/kg+ RM0.003/kg+ RM0.03/kg=RM3.39/kg
Absolutely—we’ll weave in sharp analysis or eye-catching visuals like stats and charts to level up your paper. Whether it’s crunching numbers or designing a graph, our writers make it professional and impactful, tailored to your topic.
RM 3.39 X 5%=RM0.17/kg
RM3.39/kg+ RM0.17/kg= RM3.56/kg
3.56
Cost of Labour
20+27+35+23+9=114 minute
114x 10%=11.40minute
114+11.4 =125.4 minute
125.4minute/60minute=2.09 hour
RM6 x 2.09= RM17.40/100kg
17.40/100kg =RM0.13/kg
We tackle each chunk with precision, keeping quality consistent and deadlines on track from start to finish. Whether it’s a dissertation or a multi-part essay, we stay in sync with you, delivering top-notch work every step of the way.
RM4 x 2.09= RM8.36/100kg
RM8.36/100kg =RM0.08/kg
RM5/100kg = RM0.05/kg
RM0.13/kg+ RM0.08/kg+ RM0.05/kg
= RM0.26
Yes—we’ve got it down! Our writers switch seamlessly between UK, US, Australian, or any other standards, matching your school’s exact expectations. Your paper will feel native to your system, polished and ready for wherever you’re studying.
0.26
TOTAL:
PROFIT (15%)
3.82 X 15%= 0.57
0.57
Progressive delivery is a cool option where we send your paper in chunks—perfect for big projects like theses or dissertations. You can even pay for it in installments. It’s just 10% extra on your order price, but the perks are worth it. You’ll stay in closer touch with your writer and can give feedback on each part before they move to the next. That way, you’re in the driver’s seat, making sure everything lines up with what you need. It saves time too—your writer can tweak things based on your notes without having to redo huge sections later.
Cost of reinforcement bar
3.82+0.57=4.39
Estimate the total cost of formwork to construct the suspended transfer beams (non-perimeter) size 750mm wide x 1200mm deep x 3000 mm long in 15 numbers without crossing each other. Thickness of suspended slab is 125 mm
Given:
Absolutely! If your teacher’s got feedback, you can request a free revision within 7 days of approving your paper—just hit the revision request button on your personal order page. Want a different writer to take a crack at it? You can ask for that too, though we might need an extra 12 hours to line someone up. After that 7-day window, free revisions wrap up, but you can still go for a paid minor or major revision (details are on your order page). What if I’m not satisfied with my order? If your paper needs some tweaks, you’ve got that free 7-day revision window after approval—just use the “Revision” button on your page. Once those 7 days are up, paid revision options kick in, and the cost depends on how much needs fixing. Chat with our support team to figure out the best way forward. If you feel the writer missed the mark on your instructions and the quality’s off, let us know—we’ll dig in and sort it out. If revisions don’t cut it, you can ask for a refund. Our dispute team will look into it and figure out what we can offer. Check out our money-back guarantee page for the full scoop.
12mm plywood at RM36.00 per m2
Cutting waste is 15%
0.06 m3 of props and struts per m2 above beam at RM560.00 per m3
Allow 3 uses for timber
Wastage on each use is 10%
Nails and bolts at RM2.00 per m2
2 joiners and 4 labourers take 12 hour to erect and fix this formwork (for all the 15 number of beam)
Labour cost for joiner at RM8.00 per hour
Labour cost for labourer at RM 5.50 per hour
Overhead and profit: 10%
Topic
Calculation
Cost (RM/m2)
Cost of materials
RM 36.00/m2
RM 560 0.06m3= RM 33.60/m2
RM 36.00/m2+ RM 33.60/m2=RM 69.60/m2
RM 69.60/m2+15%= RM 80.04/m2
Allow 3 uses for timber
RM 80.04/m2 3= RM 26.68/m2
RM 2.00/m2
RM 26.68/m2+ RM2.00/m2=RM28.68/m2
RM28.68/m2+10%=RM 31.55/m2
31.55
Cost of labour
RM8/hr x 2 joiners x 12hr/15x [(1.2mx 3m) + (1.2m x 0.75m)]x 2
RM 5.5/hr 4 labors 12hr / 15 [(1.2m 3m) + (1.2m 0.75m)] 2
3.38
Total of formwork
Profits 10%
34.93 x 10%=3.49
3.49
Total
The total cost of formwork to construct the suspended transfer beams (non-perimeter) size 750mm wide x 1200mm deep x 3000 mm long in 15 numbers without crossing each other is RM5186.70 (RM345.78 x 15)
Calculate the cost (per m3) of concreting a beam 400mm x 450 mm x 4000mm
Cost of concrete (ration= 1 :3 : 6)
Ordinary Portland cement = 1420 kg/m3 @ RM 10.00/50kg
Sand = 1600kg/m3 @ RM30.00 per tonne
Coarse aggregate = 1400kg/[email protected] RM 40.00 per tonne
Shrinkage, consolidation and wastage @ 5%
Cost of labour and machine (5/31/2 mixer)
Labour gang : 5 nos. At RM3.50 per hour m3
Mixer output @ 1.2 m3 per hour
Cost per of mixer including fuel is RM5.00
Additional labour for hosting and placing of concrete into beams = 0.6 hour per m3 @ RM3.50 per hour
Additional labour working around reinforcement is 0.55 hour @ RM3.50 per hour per m3
Cost of vibrator is RM 6.50 per hour, per m3
Overhead and profit is 10%
Cost of Materials
1429kg/50kg x RM10 x 1=RM284
1600kg/1000kg x RM 30 x 3=RM144
1400kg/1000kg x RM 40 x 6=RM336
RM284+RM144+RM336=RM764
RM764 x 5%=RM38.2
Total:RM764+38.20=RM802.20
RM802.20/10m3=RM80.22
80.22
Cost of Labour & Machine
5 x RM3.50 / 1.2m3= RM 14.58
5 x RM5.00 / 1.2m3= RM 20.83
0.6hour x RM3.50= RM2.10
0.55hour x RM3.50 =RM 1.93
RM6.50 x 1 = RM 6.50
RM 14.58 + RM 20.83+ RM2.10+ RM 1.93+ RM 6.50= RM45.94
45.94
TOTAL:
PROFIT (10%)
126.16 X 10%= 12.61
12.61
Cost of concrete
126.16 + 12.61= 138.78
Estimate the total cost of 1 bottom layer of BRC A7 in car porch slab measuring 2500mm x 4000mm x 150mm thick ( concrete cover = 25mm)
Given:
List price of BRC A7 is RM72.60 per sheet of 6.00m x 2.20m. A discount of 25% from price is offered by the supplier.
Laps and wastages for the BRC is 12%
Allow tying-wire and spacer block at RM1.00 per m2 of mesh reinforcement
2 labourers unload and fix 10m2of BRC A7 in car porch slab in one hour
Cost of labourer is RM45.00 per day
Overhead and profit is 10%
Cost of Materials
RM 72.60 75 %( 100-25%)=RM54.45/m2
RM 54.45/m2/(6 x 2.2)= RM 4.13/m2
RM 4.13/m2+RM 1.00/m2= RM 5.13/m2
RM 5.13/m2+12%= RM 5.75/m2
5.75
Cost of Labour
RM45/day 8hr 2 labors 1hr/10m2 = RM 1.13/m2
1.13
TOTAL:
RM 5.75/m2 + RM 1.13/m2=6.88m2
6.88
PROFIT (10%)
6.88 x 10%=0.69
0.69
Cost of BRC work
6.88+0.69
Calculate the total cost of a brick wall measuring 8 m long and 3m high with damp proof course (DPC) and “EXMET” brick reinforcement. The thickness of the brick wall is a one and half brick (1 ½ brick thick)
Given:
Material cost = RM103.50 pcs per pallet
59 pieces of brick are needed for every one square meter of half brick wall.
Wastage on brick 5%
Output is 120 bricks per hour bricklayer
Labour gang for walling is 3 bricklayer s and 2 labourers
Cement and san mortar (1:3) needed is 0.08 m3 / m2 of 1 ½ brick thick wall.
Wastage for “Exmet” is 5 %
1 bricklayer and 1 labourer can lay 82m of “exmet” brick reinforcement for 2 hour
500 bricks (1 pallet)
Mortar = RM80.00/m3
Bricklayer = RM 70.00/hour
Labourer = RM55.00/hour
Exmet (82 m long) = 250.00/m
Fibre based bituminous felt damp-proof course laid horizontally and bedded in cement and sand (1:3) mortar. Bedding mortar is disregarded since it has been included in the brickwork
1m2 of brick wall above requires 0.4m2 of DPC
Wastage 5%
Laps 5%
2 bricklayers and 1 labourer, can lay 1m2 of DPC in 0.25hour
Overhead and profit 15%
DPC = RM5.00/m2
Cost of brick
RM103.50/500= RM0.21
59 x 3 = 177pieces
Wastage of brick (5%)
177 x 105=186 pieces
Cost of brick
186 x RM0.21= RM 39.06
39.06
Cost of Labour (walling)
3 x 70 x =RM309.75
2 x 55 x = RM162.25
Total: 309.75+162.25= RM 472
472.00
Cost of Mortar
0.08 x 80 = RM6.40
6.40
Cost of Exmet
=3.33;
3.33 x 105%=3.50
RM250/82m=RM3.05
3.05 x 3.50= RM10.68
10.68
Cost of Labour (Exmet)
x 2 x 3.33=RM4.47
x 2 x 3.33=RM5.69
Total labour cost
RM4.47+ RM5.69=RM10.16
10.16
DPC
1m2=0.4m2
5%+5%=10%
0.4×110%=0.44
0.44 x RM5= RM2.20
2.20
Cost of Labour (DPC)
2 x RM70 x 0.25 x 0.4=RM14.00
1 x RM55 x 0.25 x 0.4=RM5.50
RM14.00+ RM5.50=RM19.50
19.50
Total cost of brick wall (Cost of brick, Cost of Labour (walling), Cost of Mortar, Cost of Exmet & Cost of Labour (Exmet).
39.06+472.00+6.40+10.68+10.16=538.3
538.3 x 8 x 3= 12919.20/m2
Total cost of DPC
(2.20+19.50)x8 =173.60
TOTAL of brick wall:
PROFIT (15%)
1963.92
In conclusion, cost estimation is very important in construction area. This is because when the wrong estimation of the cost per m2 will lead the loss of profits for the contractor. Therefore, the estimator must have the professional ability and cautious to do the estimation. From the solution above, we can conclude as below
2.1 answers is the rate per m3 for excavating a foundation trench starting at ground level in no exceeding depth 1.5, average 1.2m is RM 56.95.
2.2 answers is the unit rate per m3 for excavating a pit for pad is RM39.69
2.3 answers is the cost per kilogram of 25mm diameter high yield steel reinforcement bars is RM4.39
2.4 answers is the total cost of formwork to construct the suspended transfer beams (non-perimeter) size 750mm wide x 1200mm deep x 3000 mm long in 15 numbers without crossing each other is RM5186.70
2.5 answers is the cost (per m3) of concreting a beam is RM138.78, Cost for concreting a beam 400mm x 450 mm x 4000mm is RM99.92
2.6 answers is the total cost of 1 bottom layer of BRC A7 in car porch slab measuring 2500mm x 4000mm x 150mm thick ( concrete cover = 25mm) is RM 75.70
2.7 answers is the total cost of a brick wall measuring 8 m long and 3m high is RM15056.72
Tags: Cheap essay writer Australia, Cheap Essay Writing, Homework Writing Service, Research Paper AssistanceYou Want The Best Grades and That’s What We Deliver
Our top essay writers are handpicked for their degree qualification, talent and freelance know-how. Each one brings deep expertise in their chosen subjects and a solid track record in academic writing.
We offer the lowest possible pricing for each research paper while still providing the best writers;no compromise on quality. Our costs are fair and reasonable to college students compared to other custom writing services.
You’ll never get a paper from us with plagiarism or that robotic AI feel. We carefully research, write, cite and check every final draft before sending it your way.